Life in Christ New Building Plan
May 4, 2025 - Last service in the current building
May 5-17 - Demolition of the current building
May 18 - Ground Breaking
May 18 - Beginning Excavation
June 2-13 - Foundation concrete work
June 16-26 - Setting walls
June 27-July 3 - Rafters
July 4-13 - Shingling
July 14 - Siding